Project Background

Description
Anoka County, in partnership with City of Ramsey, is developing a preliminary layout for the County Highway Corridor, CSAH 83 (Armstrong Blvd NW) at the intersection with Alpine Drive. The project is in the preliminary development phase, and will include reconstructing the intersection with a single-lane roundabout, improving the safety and mobility of all modes of transportation and pedestrians by eliminating the existing two-way stop control. Construction is scheduled in Spring 2023.   

Project Goals

  • Safely accommodate all users including motor vehicles, pedestrians, and bicyclists
  • Improve storm water management and treatment
  • Reduce impacts and avoid, where appropriate, the natural resources and wetlands adjacent to the highway corridor
  • Provide efficient mobility and access for all modes of travel
  • Develop a financially responsible design that minimizes right-of-way and environmental resource impacts

Schedule
Provided below is an overview of the project schedule identifying key milestones in the process: 

  • Develop Concepts – Winter 2020 
  • Identify Preferred Alternative – Spring 2021
  • Develop Geometric Layout – Summer 2021
  • Preliminary Design – Fall 2021 to Summer 2022
  • Public Open House – Winter 2021/22
  • Final Design – Summer 2022 to Winter 2022/23
  • Construction – Spring 2023

Project Layout
Preliminary Layout


Project Contacts
If you have any questions about the proposed project or would like to comment on any aspect of the project, please contact either of the representatives below:

  • Elizabeth Markose, Project Manager
    763-324-3116; Email

  • Nicholas Dobda, Design Engineering Supervisor
    763-324-3118; Email