Construction Weekly

Welcome to the 2018 Construction Weekly!

These updates are published weekly during the construction season, with details about construction projects throughout Anoka County. A map of the 2018 Road Construction projects will be posted at the bottom of this page when it becomes available.

Subscribe to email notification of these updates by using our Notify Me list.

Updates for June 15, 2018

Bunker Lake Boulevard (CSAH 116) from Crane Street N.W. to 500 feet east of VanBuren Street N.E., in the Cities of Andover and Ham Lake
UPDATE - County Crews are tentatively scheduled to place topsoil and shap yard areas at temporary fence relocation areas during the week of June 18th.  Fence re-installation will follow, along with turf restoration.

East Main Street (CSAH 14) Signal Replacement & Roadway Rehabilitation Project from 7th Avenue (CSAH 7) to Round Lake Boulevard NW (CSAH 9) in the Cities of Anoka and Coon Rapids
UPDATE –  All construction requirements for this project have now been completed.  Modification to the existing signal system at the intersection of East Main Street and Round Lake Boulevard will take place in July.  This work will require a vertical adjustment on the existing steel signal pole bases.

Hanson Boulevard (CSAH 78) Railroad Bridge Overpass Project in the City of Coon Rapids
UPDATE – No major roadwork was attempted this past week due to utility installation continuing along the northbound boulevard.  Utility crews are in the process of installing a 30-inch diameter steel conduit under the railroad tracks.  This is expected to be completed early in the week of June 18th and will be utilized by telephone, cable television and fiber interconnect companies.  

Lake Drive (CSAH 23) Frontage Road Improvement Project from Hamline Avenue North to Village Parkway in the Cities of Circle Pines and Lexington
UPDATE – This past week, crews completed constructing the stormwater drainage swales, located south of Lake Drive.  Topsoil was placed along concrete sidewalk and pedestrian ramps that were poured and paved last week.  Shaping and grading for the various frontage roads took place at various locations this week.  Work for the week of June 18th will consist of utility relocation, primarily Xcel Energy and CenturyLink, as they continue new pole and line installation on those service roads north of Lake Drive.  Dirt crews will also be working in these same areas, grading and placing class 5 aggregate base as the utilities are relocated.

125th Avenue NE (CSAH 14) from Opal Street to 4th Avenue in the Cities of Blaine and Lino Lakes
UPDATE  - Crews began the week by grinding the existing asphalt roadway into a gravel condition.  After shaping and compacting were completed, paving crews placed the first of two asphalt layers today (June 15th) on the driving lanes in each direction for the full length of the project.  For the week of June 18th, gravel will be placed and compacted on the shoulder portion of roadway.  Placement of the final layer of asphalt is tentatively scheduled to be placed during the week of June 25th.

Metropolitan Council NAI Phase 9 Interceptor Project along East River Road (CSAH 1) near 44th Avenue in the City of Fridley
UPDATE –  For detailed information, please see the MCES project website: https://metrocouncil.org/sewerconstruction/fridleynai9

Completed Projects

East River Road (CSAH 1) & Mississippi Street (CSAH 6) Signal Replacement and Modification in the City of Fridley
UPDATE  - Completed 

Foley Blvd (CSAH 11) from Egret Blvd to Northdale Blvd (CSAH 12) in the City of Coon Rapids
UPDATE - Completed

2018 County Wide Overlay Program
CSAH 28 - Ambassador Blvd NW from Nacre Street NW to Bridgestone Drive NW & Nacre Street NW from Ambassador Blvd NW to the Anoka/Isanti County Line
UPDATE - This roadwork is scheduled to begin during the week of June 18th. No closure will be required as construction will consist of grinding the existing asphalt surface into a gravel condition.  Then crews will place two 2-inch asphalt layers over the gravel surface.