Construction Weekly

Welcome to the Construction Weekly for the 2017 Construction Season!

 

These updates are published weekly (usually Fridays) during the construction season, with details about construction projects throughout Anoka County.  A map of the 2017 Road Construction projects is posted at the bottom of this page.
     
Subscribe to email notification of these updates by using our Notify Me list.   
  
  

Update for May 26, 2017  
  


125th Avenue (CSAH 14) Reconstruction from Radisson Road (CSAH 52) to Harpers Street NE in the City of Blaine 

UPDATE

– Minor turf restoration and work items remain to be completed. Paving that was completed last week is not up to the County or public's expectations. Anoka County is working to resolve this issue with the paving contractor.
    
      
Bunker Lake Boulevard (CSAH 116) from Crane Street NW to 500 feet east of Van Buren Street NE in the Cities of Andover and Ham Lake 

UPDATE

– 
TRAFFIC CONTROL -  Bunker Lake Boulevard is now closed from just east of Prairie Road NW to just west of Goldenrod Street NW. Those who accessed Goldenrod Street NW, Anoka County Farms and the Bunker Hills Activity Center previously from the west, will now arrive from the east of those entrances and street. Those who wish to access the Copart property will continue arrive coming from the east of the entrance location. Access to County Parkway “A” will remain open as access will be available from Hanson Boulevard to Prairie Road NW. Jefferson Street NE will always remain open during the upcoming construction phases. Traffic from Terrace Road to the east end of the project limits has been shifted to the north side of Bunker Lake Boulevard as construction work has begun on the south side of the roadway.

TRAFFIC NOTE: Butternut Street NW will be open to traffic on Friday, May 26th after paving operations are completed. On Tuesday, May 30th, Goldenrod Street NW will be closed from 137th Lane NW to Bunker Lake Boulevard for the purpose of installing new sanitary sewer pipe and watermain that will service the Anoka County Parks Activity Center. This closure will be in place for approximately two weeks, depending on the weather. Residents in the Shadowbrook Development should utilize Butternut Street NW to exit and enter Bunker Lake Boulevard during this closure.

CONSTRUCTION SCHEDULE - Two layers of asphalt surfacing were placed this past week from a point just east of Goldenrod Street to the Copart entrance. With the completion of this paving sequence, traffic will be switched to these newly constructed lanes beginning on Friday, May 26th. After the traffic switch, dirt crews will begin removing the existing asphalt from Anoka County Farms to Goldenrod Street during the week of May 29th. On Tuesday, May 30th, the sewer crew will begin work on watermain and sanitary sewer installation on Goldenrod Street beginning at 137th Lane NW and continuing to work south, across Bunker Lake Boulevard. As stated earlier, this work will take approximately two weeks to complete and will require this portion of Goldenrod Street to be closed to through traffic. Crews continue with various concrete pours associated with the steel sheeting wall on the north side of Bunker Lake Boulevard. Various utility relocation and installation work continues Bunker Lake Boulevard, east of Jefferson Street NE.

  
         
Foley Blvd (CSAH 11) from Egret Blvd to Northdale Blvd (CSAH 12) in the City of Coon Rapids

UPDATE

During the week of May 29th, concrete crews will install concrete curb & gutter from 111th Avenue to a point 300 feet south of Northdale Boulevard on the southbound shoulder and portions of the center island median. Concrete sidewalk and concrete entrances will also be placed after curb placement is completed. Storm sewer crossings from the southbound lanes to the northbound lanes of Foley Boulevard were completed this past week. Asphalt paving is tentatively scheduled for the week of June 5th.
    
    

Metropolitan Council NAI Phase 9 Interceptor Project along East River Road (CSAH 1) near 44th Avenue in the City of Fridley

UPDATE

– The current lane closure on southbound East River Road (CSAH 1) has been lifted. Work on the replacing the existing sanitary system is scheduled to begin in early July. 
 

MN/DOT Scheduled Bridge/Road Closure on 4th Avenue (CSAH 31) in the City of Anoka

UPDATE

– On Tuesday, May 30th, crews will close the 4th Avenue bridge over TH 10 to begin removing unsound concrete from the bottom of the bridge pier caps. For the safety of the public and the workers, it’s necessary to close the bridge when this phase of the work begins, and keep it closed until the repairs are completed on both piers. Mn/DOT estimates this will take 5 weeks.

2017 County-Wide Overlay Program

County Road 15 (East Bethel Blvd) from CSAH 22 (Viking Blvd NE) to County Road 74 (213th Ave NE) in the City of East Bethel

UPDATE–  Asphalt paving crews have completed placing the first of two, 2-inch asphalt lifts this past week. During the week of May 29th, crews will pave the remaining roadway lift and private entrance approaches. After all paving is completed, gravel will be placed along the roadway shoulder.
  
County State Aid Highway 25 (229th Avenue) from 550 feet west of CR 15 (Durant Street) to CSAH 85 (Typo Creek Drive NE) in Linwood Township

UPDATE–  Reclaiming of the existing roadway and entrance removals have been completed. The road closure has been re-scheduled for May 31st. This closure is required to replace an existing culvert, and is expected to take two days to complete. Shaping of the reclaimed roadway gravel will also occur during the upcoming week, with asphalt paving tentatively scheduled for the week of June 5th.


  
 
 
 
 
A map of the 2017 Construction Projects can be found here:

2017 Construction Projects