Construction Weekly

Welcome to the Construction Weekly for the 2017 Construction Season!

 

These updates are published weekly (usually Fridays) during the construction season, with details about construction projects throughout Anoka County.  A map of the 2017 Road Construction projects is posted at the bottom of this page.
     
Subscribe to email notification of these updates by using our Notify Me list.   
  
  

Update for August 18, 2017  
  


125th Avenue (CSAH 14) Reconstruction from Radisson Road (CSAH 52) to Harpers Street NE in the City of Blaine 

UPDATE

– Paving that was completed recently is not up to County or public expectations. Anoka County is working to resolve this issue with the paving contractor.
    
      
Bunker Lake Boulevard (CSAH 116) from Crane Street NW to 500 feet east of Van Buren Street NE in the Cities of Andover and Ham Lake 

UPDATE

– Bunker Lake Boulevard is scheduled to be re-opened to the traveling public by the afternoon of Friday, August 18th. Completed and uncompleted signaled intersections will be in an all-way stop condition at the time of the opening and will remain that way until all concrete sidewalk has been placed. Traffic will be in a single lane in each direction as crews continue with various task along the project. Storm sewer installation on the westbound lanes from Jefferson Street to the eastern project limits is scheduled to be completed by Monday, August 21st. Concrete crews are also scheduled to continue placing concrete in the median areas during the upcoming week, beginning at the west end of the project and commencing east. Dirt crews will begin roadway grading on the remaining unconstructed portion the westbound lane, after sewer crews are completed. Dirt crews will also construct bike path grade at various locations along the project. Minor wood plank installation remains to be completed on the sound wall between Sycamore Street NW to Prairie Road NW. Traffic signal installation work at Prairie Road has been completed, with Sycamore Street scheduled to be completed earlier in the upcoming week. Signal work at Jefferson Street will resume after remaining concrete curb is completed,
 

Foley Blvd (CSAH 11) from Egret Blvd to Northdale Blvd (CSAH 12) in the City of Coon Rapids 

Update -

This past week, crews removed the remaining temporary water main on the west side of Foley Boulevard and south of Northdale Boulevard. Crews also completed installing all required water services to the new water main. Dirt crews have completed grading and placing gravel on the eastbound lane of Northdale Boulevard. Crews are scheduled to complete grading and placing gravel on northbound Foley Boulevard from 113th Avenue to Northdale Boulevard during the week of August 21st. Storm sewer will be install on westbound Northdale Boulevard, west of the Foley intersection.
 
   

Metropolitan Council NAI Phase 9 Interceptor Project along East River Road (CSAH 1) near 44th Avenue in the City of Fridley

UPDATE - 

For more detailed information, please see the MCES project website @www.metrocouncil.org/sewerconstruction/fridleynai9
 

East River Road (CSAH 1) & Mississippi Street (CSAH 6) Signal Replacement and Modification in the City of Fridley

UPDATE

– Crews have begun with saw cutting asphalt, concrete curb and concrete sidewalk in preparation for removal. Crews will begin with the installation of a temporary signal system while the existing signal system is removed and replaced. 
 
 
 

East Main Street (CSAH 14) Signal Replacement & Roadway Rehabilitation Project, from 7th Avenue (CSAH 7) to Round Lake Boulevard NW (CSAH 9) in the Cities of Anoka and Coon Rapids


UPDATE

– Various asphalt and concrete saw cutting was completed this past week in preparation for removal during the week of August 21st. Traffic will be relocated to the north side of Main Street to accommodate the removal process. Crews will also begin repairs on storm sewer structures along the south edge of the roadway. No detour is scheduled for this project, but drivers should expect delays. Construction is scheduled to be completed by October 20th, 2017. 



2017 County-Wide Overlay Program


  

 

  


County State Aid Highway 132 (85th Avenue NW) from CSAH 1 (East River Road) to 250’ west of Cottonwood St in the City of Coon Rapids


UPDATE

Minor turf restoration and sign installation are scheduled to be completed during the week of August 21st.


 

County State Aid Highway 1 (East River Road) from Kimball Street NE to TH 610 in the City of Coon Rapids


UPDATE 

Rain has delayed progress this past week as remaining work on the outside lanes is now scheduled to be completed on Friday, August 18th. Traffic will be moved to the outside lanes on Monday, August 21st, so crews can begin work on island curb removal and storm structure restoration on the inside lanes.


 


County State Aid Highway 24 (Norris Lake Road) from CR 70 (Jarvis Street NW) to CSAH 5 (Nowthen Boulevard NW) in the City of Nowthen
UPDATE

Reclamation of the existing asphalt has been completed. The first of two asphalt layers is scheduled to be placed during the week of August 21st.



County Road 89 (Sugar Bush Road NW) from County State Aid Highway 24 (Norris Lake Road) from CR 70 (223rd Avenue NW) in the City of Nowthen
UPDATE– 

Reclamation of the existing asphalt has been completed. The first of two asphalt layers is scheduled to be placed during the week of August 21st.


 



    
County Road 15 (East Bethel Blvd) from CSAH 22 (Viking Blvd NE) to County Road 74 (213th Ave NE) in the City of East Bethel
UPDATE – 

This project is completed.

 

County State Aid Highway 26 (229th Avenue) from 550 feet west of CR 15 (Durant Street) to CSAH 85 (Typo Creek Drive NE) in Linwood Township
UPDATE –

This project is completed.


 

County State Aid Highway 78 (Hanson Boulevard) Left Turn Lane Modifications at the intersection of Station Parkway NW in the City of Andover


UPDATE

This project is completed. 


  

County Road 158 (165th Avenue NW) from CSAH 7 (165th Avenue NW) to County Road 58 (Valley Drive NW) in the City of Andover
UPDATE

This project is completed.

County Road 58 (181st Avenue NW) from CSAH 78 (Flamingo Street NW) to Palm Street NW/Cedar Drive in the Cities of Andover and Oak Grove


UPDATE

This project is completed. 

County State Aid Highway 24 (229th Avenue NW) By-Pass Lane construction from 380 feet west of Arrowhead Street NW to 240 feet east of Arrowhead Street NW in the City of St. Francis
UPDATE –

This project is completed. 

County State Aid Highway 24 (237th Avenue NE) from CSAH 13/CR 73 (University Avenue Extension) to TH 65 (Central Avenue NE) in the Cities of Bethel and East Bethel
UPDATE –

This project is completed. 


  

County Road 72 (Rum River Boulevard NW) from Rum River Park North Park Entrance to 300 feet south of 235th Avenue NW in the City of St. Francis
UPDATE –

This project is completed. 

 

 

 

 

 
 
A map of the 2017 Construction Projects can be found here: 

 

2017 Construction Projects